Capitol Improvement Project Status


Contact Sun Mountain property manager for more details

Front walk-way and raised plant bed upgrade project

9/4/2024 Update:  HOA Owner committee established. Stay tuned!

Building C Siding

5/29/2024 Update:  The building C siding project has been completed as of July 2023. The Contractor was Esquivel Roofing and Siding. Garage doors were painted and new lights installed in fall 2023.

10/17/2022 Update:  The building C siding project is tentatively scheduled to begin in May 2023.  Siding material has a 4-5 month leadtime and will be placed on order in November 2022. 

Building A Siding

5/29/2024 Update: The building A siding project has been completed as of July 2022.  The Contractor was Esquivel Roofing and Siding. Garage doors were painted and new lights installed in fall 2023.

10/17/2022 Update:  Building A siding project has been completed July 2022! Contractor was Esquivel Roofing and Siding.  Remaining loose ends include painting the garage doors and electrical boxes, and replacing the lights on the garage.

1/29/2021 Update:  The building A siding project is on pause, waiting for the final batch of siding material - and for snow melt in the spring!

Building A and C - Roof replacement

1/29/2021 Update:  Project was completed in Summer 2020.